Playford relocation and associated transmission line diversions
Client:
ElectraNet
Location:
Port Augusta
Start:
September 2008
Finish:
December 2010
Contract type:
Engineer, Procure, Construct (EPC)
Value:
Capital value of total project < $50m
Initial value of ETSA Utilities' contract - $43m
Description
Portion 1 - Substation design, supply, construction and commissioning
Portion 2 - Transmission line design, supply, construction and commissioning
Portion 3 - Communications design, supply, construction and commissioning
This substation relocation scope included:
- Construction of 160MVA transformer bays with associated 275 kV plant
- Construction of a new 132kV yard bench, which required in excess of 50,000 m3 of bulk earthworks
- Design, supply, installation and commissioning of the required 132kV plant at Davenport & Playford substations
- Procurement, design, installation, and commissioning of new protection and control systems, radio and fibre links between substations
- On site refurbishment of 1 x160 MVA transformer
Overview of key contract successes and learnings:
- 58000 man-hours of work to date with zero loss time injuries
- Comprehensive internal design which led to minimised onsite issues during the construction phase
- Project controls ensured high levels of efficiencies on the project
- Detailed planning and co-ordination reduced the effect of adverse weather and outage minimising
- Project currently ahead of time and under budget